WE'RE RENOVATING

Beginning January 3, 2024, please utilize our main entrance for regular drop off and pick-ups. Also, if you need to come into the building, please utilize the staff/visitor parking lot near the Main Entrance, and don't forget to bring your ID. Late arrivals and early dismissals will be handled at the new Attendance window located by the Main Office/Main Entrance.

4/10/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - D-hall paint and priming are nearing completion and ceiling grid is ongoing. all underground piping, rough-ins, and slab work complete.

  • Boy's Locker Room - New complete, next we move over to the Girl's Locker Room

  • Chorus Room Addition - MCM panels and roof nearing completion

  • Planning for Summer work to include Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall

  • Summer work to also include moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers

  • Anticipated Substantial Final Completion - September 24, 2025

3/12/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - (D-hall) Demolition activities complete. Mechanical, electrical, and plumbing roughins are ongoing. All underground piping and slab work is complete.

  • Boys' Locker Room-Ceilings, painting, mechanical, plumbing, and electrical ongoing

  • Chorus Room Addition-MCM Panels and roof nearing completion

  • Planning for Summer work to include the Commons, Cafeterias, Kitchen, Library Media Center, Girls' Locker Room, Band, Chorus, Drama and C-Hall

  • Summer work to include moving everyone in the trailers back to 'D-Hall'

  • Anticipated Substantial Final Completion-September 24, 2025

2/13/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - (D-hall) Demolition activities near completion. Mechanical, electrical, and plumbing roughins are ongoing

  • Boy's Locker Room - Masonry, painting, mechanical, plumbing, and electrical ongoing

  • Chorus room addition - Brick masonry and windows complete

  • Anticipated Substantial Final Completion - September 24, 2025

11/14/2023 Update

  • Plumbing, electrical, mechanical, and tiling. flooring, sheetrock, and roofing within Phase 1 is ongoing

  • Continuing to install grid work/ceilings

  • Anticipate classroom completion by December 2023

  • Completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023

  • Plan for the next move has begun

  • School Counseling modular and new classroom module

  • Anticipated Substantial Final Completion-September 24, 2025

10/10/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going

  • Flooring installation has begun

  • Continuing to install grid work/ceilings

  • Anticipate classroom completion by December 2023

  • Hopeful completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023

  • Plan for the next move has begun

  • School Counseling modular and new classroom modular

  • Anticipated Substantial Final Completion-September 24, 2025

September, 2023 Update

8/8/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going

  • Anticipate completing the new entrance, security vestibule, administrative/guidance offices, and clinic by the end of first semester 2023

  • Phase 2 construction progressing well - remainder of A-hall, boys' locker room

  • Moving of furniture into new modular classrooms has been completed

  • Paving and curbing completed

  • Anticipated Substantial Final Completion-September 24, 2025

7/11/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing and sheetrock within Phase 1 is on-going

  • Anticipate completing the new entrance, security vestibule, administrative/guidance offices and clinic by the end of first semester 2023

  • Began construction of Phase 2 - remainder of A-Hall, boys locker room

  • Last 2 modular classroom trailers delivered

  • Fire protection waterline being installed

  • Anticipated Substantial Final Completion - September 24, 2025

4/11/2023 Update

  • Demolition work within the existing building is on-going

  • New Chorus addition has been added to phase 1

  • Anticipate summer completion the new main entrance, security vestibule, administrative/guidance offices and clinic

  • Plan to begin phase 2-June, 2023

  • Anticipated substantial final completion-July 15, 2025

Phase 1

Renovations Update Video-Main Entrance, Extended Learning Area & Restrooms