WE'RE RENOVATING

7/9/2024 Update

  • D Hall (300 Hall_ - Completed ahead of schedule, CO received June 7, 2024

  • Girls Locker Room, Commons, Cafeteria, Kitchen, Duke Rock Conversion - All currently under construction

  • Media Center, Band, Chorus, Drama, and C-Hall - All currently under construction

  • Moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers - Work Completed

  • Anticipated Substantial Final Completion - September 24, 2025

6/12/2024 Update

  • D Hall (300 Hall) - Completed ahead of schedule, CO received June 7, 2024

  • Girls Locker Room, Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall - All currently under construction

  • Moving everyone in trailers back to D-Hall and moving the majority of C-Hall out to trailers

  • Anticipated Substantial Final Completion - September 24, 2025

5/14/2024 Update

  • Boys' Locker Room - Complete and in use

  • Girls' Locker Room - Currently under construction

  • Planning for summer work to include Commons, Cafeteria, Kitchen, Library Media Center, Band, Chorus, Drama, and C-Hall

  • Summer work to also include moving everyone in trailers back to D-Hall (300 Hall) and moving majority of C-Hall out to trailers

  • Construction schedule will accommodate upcoming elections on June 17, 2024

  • Anticipated Substantial Final Completion - September 24, 2025

4/10/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - D-hall paint and priming are nearing completion and ceiling grid is ongoing. all underground piping, rough-ins, and slab work complete.

  • Boy's Locker Room - New complete, next we move over to the Girl's Locker Room

  • Chorus Room Addition - MCM panels and roof nearing completion

  • Planning for Summer work to include Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall

  • Summer work to also include moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers

  • Anticipated Substantial Final Completion - September 24, 2025

3/12/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - (D-hall) Demolition activities complete. Mechanical, electrical, and plumbing roughins are ongoing. All underground piping and slab work is complete.

  • Boys' Locker Room-Ceilings, painting, mechanical, plumbing, and electrical ongoing

  • Chorus Room Addition-MCM Panels and roof nearing completion

  • Planning for Summer work to include the Commons, Cafeterias, Kitchen, Library Media Center, Girls' Locker Room, Band, Chorus, Drama and C-Hall

  • Summer work to include moving everyone in the trailers back to 'D-Hall'

  • Anticipated Substantial Final Completion-September 24, 2025

2/13/2024 Update

  • Phase 1 - Punchlist items remain to be completed

  • Phase 2 - (D-hall) Demolition activities near completion. Mechanical, electrical, and plumbing roughins are ongoing

  • Boy's Locker Room - Masonry, painting, mechanical, plumbing, and electrical ongoing

  • Chorus room addition - Brick masonry and windows complete

  • Anticipated Substantial Final Completion - September 24, 2025

11/14/2023 Update

  • Plumbing, electrical, mechanical, and tiling. flooring, sheetrock, and roofing within Phase 1 is ongoing

  • Continuing to install grid work/ceilings

  • Anticipate classroom completion by December 2023

  • Completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023

  • Plan for the next move has begun

  • School Counseling modular and new classroom module

  • Anticipated Substantial Final Completion-September 24, 2025

10/10/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going

  • Flooring installation has begun

  • Continuing to install grid work/ceilings

  • Anticipate classroom completion by December 2023

  • Hopeful completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023

  • Plan for the next move has begun

  • School Counseling modular and new classroom modular

  • Anticipated Substantial Final Completion-September 24, 2025

September, 2023 Update

8/8/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going

  • Anticipate completing the new entrance, security vestibule, administrative/guidance offices, and clinic by the end of first semester 2023

  • Phase 2 construction progressing well - remainder of A-hall, boys' locker room

  • Moving of furniture into new modular classrooms has been completed

  • Paving and curbing completed

  • Anticipated Substantial Final Completion-September 24, 2025

7/11/2023 Update

  • Plumbing, electrical, mechanical, framing, roofing and sheetrock within Phase 1 is on-going

  • Anticipate completing the new entrance, security vestibule, administrative/guidance offices and clinic by the end of first semester 2023

  • Began construction of Phase 2 - remainder of A-Hall, boys locker room

  • Last 2 modular classroom trailers delivered

  • Fire protection waterline being installed

  • Anticipated Substantial Final Completion - September 24, 2025

4/11/2023 Update

  • Demolition work within the existing building is on-going

  • New Chorus addition has been added to phase 1

  • Anticipate summer completion the new main entrance, security vestibule, administrative/guidance offices and clinic

  • Plan to begin phase 2-June, 2023

  • Anticipated substantial final completion-July 15, 2025

Phase 1

Renovations Update Video-Main Entrance, Extended Learning Area & Restrooms