WE'RE RENOVATING
7/9/2024 Update
D Hall (300 Hall_ - Completed ahead of schedule, CO received June 7, 2024
Girls Locker Room, Commons, Cafeteria, Kitchen, Duke Rock Conversion - All currently under construction
Media Center, Band, Chorus, Drama, and C-Hall - All currently under construction
Moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers - Work Completed
Anticipated Substantial Final Completion - September 24, 2025
6/12/2024 Update
D Hall (300 Hall) - Completed ahead of schedule, CO received June 7, 2024
Girls Locker Room, Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall - All currently under construction
Moving everyone in trailers back to D-Hall and moving the majority of C-Hall out to trailers
Anticipated Substantial Final Completion - September 24, 2025
5/14/2024 Update
Boys' Locker Room - Complete and in use
Girls' Locker Room - Currently under construction
Planning for summer work to include Commons, Cafeteria, Kitchen, Library Media Center, Band, Chorus, Drama, and C-Hall
Summer work to also include moving everyone in trailers back to D-Hall (300 Hall) and moving majority of C-Hall out to trailers
Construction schedule will accommodate upcoming elections on June 17, 2024
Anticipated Substantial Final Completion - September 24, 2025
4/10/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - D-hall paint and priming are nearing completion and ceiling grid is ongoing. all underground piping, rough-ins, and slab work complete.
Boy's Locker Room - New complete, next we move over to the Girl's Locker Room
Chorus Room Addition - MCM panels and roof nearing completion
Planning for Summer work to include Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall
Summer work to also include moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers
Anticipated Substantial Final Completion - September 24, 2025
3/12/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - (D-hall) Demolition activities complete. Mechanical, electrical, and plumbing roughins are ongoing. All underground piping and slab work is complete.
Boys' Locker Room-Ceilings, painting, mechanical, plumbing, and electrical ongoing
Chorus Room Addition-MCM Panels and roof nearing completion
Planning for Summer work to include the Commons, Cafeterias, Kitchen, Library Media Center, Girls' Locker Room, Band, Chorus, Drama and C-Hall
Summer work to include moving everyone in the trailers back to 'D-Hall'
Anticipated Substantial Final Completion-September 24, 2025
2/13/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - (D-hall) Demolition activities near completion. Mechanical, electrical, and plumbing roughins are ongoing
Boy's Locker Room - Masonry, painting, mechanical, plumbing, and electrical ongoing
Chorus room addition - Brick masonry and windows complete
Anticipated Substantial Final Completion - September 24, 2025
11/14/2023 Update
Plumbing, electrical, mechanical, and tiling. flooring, sheetrock, and roofing within Phase 1 is ongoing
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom module
Anticipated Substantial Final Completion-September 24, 2025
10/10/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Flooring installation has begun
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Hopeful completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom modular
Anticipated Substantial Final Completion-September 24, 2025
September, 2023 Update
8/8/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices, and clinic by the end of first semester 2023
Phase 2 construction progressing well - remainder of A-hall, boys' locker room
Moving of furniture into new modular classrooms has been completed
Paving and curbing completed
Anticipated Substantial Final Completion-September 24, 2025
7/11/2023 Update
Plumbing, electrical, mechanical, framing, roofing and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices and clinic by the end of first semester 2023
Began construction of Phase 2 - remainder of A-Hall, boys locker room
Last 2 modular classroom trailers delivered
Fire protection waterline being installed
Anticipated Substantial Final Completion - September 24, 2025
4/11/2023 Update
Demolition work within the existing building is on-going
New Chorus addition has been added to phase 1
Anticipate summer completion the new main entrance, security vestibule, administrative/guidance offices and clinic
Plan to begin phase 2-June, 2023
Anticipated substantial final completion-July 15, 2025