WE'RE RENOVATING
Beginning January 3, 2024, please utilize our main entrance for regular drop off and pick-ups. Also, if you need to come into the building, please utilize the staff/visitor parking lot near the Main Entrance, and don't forget to bring your ID. Late arrivals and early dismissals will be handled at the new Attendance window located by the Main Office/Main Entrance.
4/10/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - D-hall paint and priming are nearing completion and ceiling grid is ongoing. all underground piping, rough-ins, and slab work complete.
Boy's Locker Room - New complete, next we move over to the Girl's Locker Room
Chorus Room Addition - MCM panels and roof nearing completion
Planning for Summer work to include Commons, Cafeteria, Kitchen, Media Center, Band, Chorus, Drama, and C-Hall
Summer work to also include moving everyone in trailers back to D-Hall and moving majority of C-Hall out to trailers
Anticipated Substantial Final Completion - September 24, 2025
3/12/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - (D-hall) Demolition activities complete. Mechanical, electrical, and plumbing roughins are ongoing. All underground piping and slab work is complete.
Boys' Locker Room-Ceilings, painting, mechanical, plumbing, and electrical ongoing
Chorus Room Addition-MCM Panels and roof nearing completion
Planning for Summer work to include the Commons, Cafeterias, Kitchen, Library Media Center, Girls' Locker Room, Band, Chorus, Drama and C-Hall
Summer work to include moving everyone in the trailers back to 'D-Hall'
Anticipated Substantial Final Completion-September 24, 2025
2/13/2024 Update
Phase 1 - Punchlist items remain to be completed
Phase 2 - (D-hall) Demolition activities near completion. Mechanical, electrical, and plumbing roughins are ongoing
Boy's Locker Room - Masonry, painting, mechanical, plumbing, and electrical ongoing
Chorus room addition - Brick masonry and windows complete
Anticipated Substantial Final Completion - September 24, 2025
11/14/2023 Update
Plumbing, electrical, mechanical, and tiling. flooring, sheetrock, and roofing within Phase 1 is ongoing
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom module
Anticipated Substantial Final Completion-September 24, 2025
10/10/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Flooring installation has begun
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Hopeful completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom modular
Anticipated Substantial Final Completion-September 24, 2025
September, 2023 Update
8/8/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices, and clinic by the end of first semester 2023
Phase 2 construction progressing well - remainder of A-hall, boys' locker room
Moving of furniture into new modular classrooms has been completed
Paving and curbing completed
Anticipated Substantial Final Completion-September 24, 2025
7/11/2023 Update
Plumbing, electrical, mechanical, framing, roofing and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices and clinic by the end of first semester 2023
Began construction of Phase 2 - remainder of A-Hall, boys locker room
Last 2 modular classroom trailers delivered
Fire protection waterline being installed
Anticipated Substantial Final Completion - September 24, 2025
4/11/2023 Update
Demolition work within the existing building is on-going
New Chorus addition has been added to phase 1
Anticipate summer completion the new main entrance, security vestibule, administrative/guidance offices and clinic
Plan to begin phase 2-June, 2023
Anticipated substantial final completion-July 15, 2025