WE'RE RENOVATING
11/14/2023 Update
Plumbing, electrical, mechanical, and tiling. flooring, sheetrock, and roofing within Phase 1 is ongoing
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom module
Anticipated Substantial Final Completion-September 24, 2025
10/10/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Flooring installation has begun
Continuing to install grid work/ceilings
Anticipate classroom completion by December 2023
Hopeful completion of the new Entrance, Security Vestibule, Administrative/Guidance Offices, and Clinic by December 2023
Plan for the next move has begun
School Counseling modular and new classroom modular
Anticipated Substantial Final Completion-September 24, 2025
September, 2023 Update
8/8/2023 Update
Plumbing, electrical, mechanical, framing, roofing, and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices, and clinic by the end of first semester 2023
Phase 2 construction progressing well - remainder of A-hall, boys' locker room
Moving of furniture into new modular classrooms has been completed
Paving and curbing completed
Anticipated Substantial Final Completion-September 24, 2025
7/11/2023 Update
Plumbing, electrical, mechanical, framing, roofing and sheetrock within Phase 1 is on-going
Anticipate completing the new entrance, security vestibule, administrative/guidance offices and clinic by the end of first semester 2023
Began construction of Phase 2 - remainder of A-Hall, boys locker room
Last 2 modular classroom trailers delivered
Fire protection waterline being installed
Anticipated Substantial Final Completion - September 24, 2025
4/11/2023 Update
Demolition work within the existing building is on-going
New Chorus addition has been added to phase 1
Anticipate summer completion the new main entrance, security vestibule, administrative/guidance offices and clinic
Plan to begin phase 2-June, 2023
Anticipated substantial final completion-July 15, 2025
Phase 1
BUS LOOP/PARENT DROP OFF LOOP UPDATES

Early Student Pick-Ups: If you need to pick up a student early and it is 2:15 PM or later, please be sure to send in a note, and pick up your student on the parent loop side. For early pick-ups prior to 2:15, students will exit through the main entrance by the library.